American Packaging Site Visit

The American Packaging Corporation office addition continues to remain on schedule for December completion.  All structural steel and exterior metal studs are now complete.  Rough-in work is moving forward at the interior.  Ductwork, sprinkler lines, plumbing, and electrical  work are well underway.  Brick and metal panel façade work will begin shortly, with aluminum storefront and curtain wall following right behind. The new 74 space parking lot has been prepared for concrete which will be completed next month.